Hot and cold calls reduced by 50% in the first year. Energy costs reduced by £100k over two years. Maintenance time prioritised by exception reporting from data analysis of plant condition.

Demand Logic worked closely with Optimum FM and Chartwell Controls to provide detailed analysis of the HVAC and BMS performance. Actions were identified to improve the internal environment of the office spaces whilst reducing energy costs.

The delivered savings paid for the cost of the Demand Logic service within a few months and the service has been regularly renewed.